Improvement and Rehabilitation of Mirijjawila – Suriyawewa Road

Road Development Authority (RDA) was the Employer as well as the Engineer of the project. The project had been proposed under local bank funds for rehabilitation and improvement of 23.34km length from 5km to 8.34km. ED&PMC worked as the design consultant of the contractor. ED&PMC carried out Highway Designs and the Hydrological Study.

Client : CML – MTD Constructions (pvt) Ltd
Commencement Date: April 2013
Period : 10 months
Read More

Feasibility Study of Proposed Expressway/Railway Line from Hambanthota Seaport to Airport

This expressway and railway section linked the proposed industrial zone in Hambanthota to the proposed extension on Southern Expressway. The feasibility study carried out to determine suitable trace for proposed /Railway linking Hambanthota Sea port and new Maththala airport and its feasibility. Road Development Authority (RDA) was the Employer of the project. The project had been consisting of 25km length of expressway and three interchanges/intersections. The project promoter was China Harbour Engineering Company Ltd. He funded the study. ED&PMC involved technical work of the study as a sub-consultant of the expressway work.

ED&PMC carried out Survey, Investigation, Preliminary Designs, Preparation of Land Acquisition Plans, Preliminary Structural Designs, Pavement Design, Preparation of Cost estimates & Planning Documents, Preparation of Tender Documents.

Client : Skills International (Pvt) Ltd
Commencement Date: March 2013
Period : 12 months
Location: Hambanthota
Read More